South Africa: Supreme Court of Appeal

You are here:
SAFLII >>
Databases >>
South Africa: Supreme Court of Appeal >>
1990 >>
[1990] ZASCA 127
| Noteup
| LawCite
Van Streepen & Germs (Pty) Ltd. v Government of the Republic of South Africa (113/89) [1990] ZASCA 127 (1 October 1990)
Download original files |
CG CASE NUMBER: 113/89
IN THE SUPREME COURT OF SOUTH AFRICA (APPELLATE DIVISION)
In the matter between:
VAN STREEPEN & GERMS (PROPRIETARY)
LIMITED Appellant
and
THE GOVERNMENT OF THE REPUBLIC OF
SOUTH AFRICA Respondent
CORAM: JOUBERT ACJ, NESTADT, F H GROSSKOPF JJA, NICHOLAS et NIENABER AJJA
HEARD: 20 AUGUST 1990
DELIVERED: 1 OCTOBER 1990
JUDGMENT NIENABER AJA
2
The point in this appeal is whether a document, issued to a building
contractor during the course of work and termed a variation order,
amended the
basis on which the contractor was to be paid from rates fixed in advance to a
fair and reasonable remuneration to be
determined afterwards.
The building
contractor was the plaintiff in the court below and is the appellant in this
one. The building owner was the defendant
and is now the respondent. I shall
continue to refer to them as the plaintiff and the defendant respectively.
The plaintiff in 1975 tendered for the
construction of the no 1 military hospital complex at
Voortrekkerhoogte described in the tender documents as
"... a ten storey main hospital buiiding, a separate boiler house and workshops connected to the hospital building by a service tunnel; a separate building providing temporary accommodation for patients arriving by helicopter; and site works comprising roads, parking areas, retaining walls, access bridge
3
etc. The buildings are of a framed reinforced concrete construction filled in with brick walls externally and internally. Mechanical and electrical services are included in this contract."
- for a composite sum of R21 840 000,00. The plaintiff's
tender, one of several, was accepted by the defendant,
acting through the
Department of Public Works (herein-
after referred to simply as "the
department"). Contract
no 25363 was thereupon formally concluded between
the
parties, comprising the articles of agreement and
conditions of contract,
a specification, the drawings
("A1-24"), and a schedule of quantities. The site was
handed over to the plaintiff on 10 September 1975. The
agreed period of completion was 54 months but, as
sometimes happens in matters of this sort, expectations
exceeded execution and execution exceeded the contract
period. Although the character and scope of the work
remained essentially the same, the work was only
completed in 1983 at a cost, taking the priced rates but
4
also escalation into account, of R35 508 862,00.
One reason, at least, for this phenomenal
increase was that tenderers were invited to tender on the
footing of
provisional (as opposed to firm) bills of
guantities, which, moreover,
contained a number of
provisional sums (i.e. items with
unpredictable
quantities), all of which were in turn compiled on
the
strength of preliminary sketch plans (as opposed to
detailed working
drawings). A contract sum, calculated
by applying fixed rates to imprecise
guantities, was
bound to differ from the sum ultimately produced once
the
work had been completed and the quantities finally
measured. (Cf MINISTER OF PUBLIC WORKS v W J M
CONSTRUCTION CO
(PTY) LTD 1983 (3) SA 58 (A) at 64 B-F.)
"Bills of Quantities" are defined in the
conditions of contract to mean
"the document attached to this Contract in which are entered the quantities of work, labour, materials, and articles required for
5
the execution of this Contract. The words 'Schedule of Quantities' shall mean the Bills of Quantities with the rates or prices of the items at which the Department of Public Works agrees to pay the contractor."
The word "provisional" was used, in
relation to the bills
of quantities, to convey to prospective tenderers
that
all quantities inserted in the bills (and not only those
which by
their very nature could not be assessed in
advance) were imprecise and might,
on eventual
remeasurement, prove to have been inaccurately estimated.
This somewhat untidy procedure was adopted in
an effort to regain lost time. The decision to erect a
comprehensive
military hospital in the vicinity of
Pretoria had in fact been taken as early as 1972. A site
had been selected
at Verwoerdburg and the preparation of
bills of quantities was well advanced
when a geological
report revealed that the site was not suitable for
its
designated purpose because of the danger of dolomitic
sinkholes. A fresh site was eventually located at
6
Voortrekkerhoogte. The project had by now become
decidedly urgent. That
was the reason why it was
resolved to prepare provisional bills of quantities,
containing
several provisional amounts, on the basis of
preliminary architectural and structural sketch plans,
and to call for
tenders accordingly.
Tenderers were furnished with, inter alia, the
set of sketch plans (A1-24), the provisional bills of
quantities as well as these express warnings:
"Provisional Bills of Quantities. All the work in these bills of quantities has been measured provisionally from the sketch plans and will be remeasured as executed and paid for according to prices in the bills of quantities and any unexpended amounts shall be deducted from the amount of the contract sum. The quantities in these provisional bills of quantities are not to be used for ordering materials.
Provisional Sums.
All provisional sums shall be expended as directed by the engineer and any balance remaining shall be deducted from the amount of the contract sum. All provisional sums are nett and do not allow for 5% cash discount.
7
The contractor may allow for profit if reguired.
Procedure for carrying out the works. Contractors are advised that, at the date of handing over the site, only architectural and structural working drawings will be available and it is anticipated detail working drawings will not be available for at least 12 months after the date of handing over the site."
Tenderers were accordingly in effect told to
discount, in
the rates quoted by them, the risk of errors in
the
estimation of quantities.
This also appears from the contract documents
which the plaintiff signed after its tender was accepted.
The contract
documents made it plain that the defendant
was not contractually committed to
the estimates of
quantities contained in the provisional bills of
guantities and that payment for items for which rates had
been quoted would only be f inalised once the work had
been measured and valued, by applying the unit rates to
the measured quantities.
8
Clause 3 of the conditions of contract, sub-
clause (iii) in particular, is important. The clause
reads:
"3. (i) The Contractor shall receive payment only for the Works actually executed and accepted.
(ii) ...
(iii) Without invalidating the Contract, the Engineer shall have the right by means of an Order in Writing, by varying the Drawings, Specification and Bills of Quantities, to increase or decrease the quantities of any item or items or to omit any item or items or to insert any additional item or items provided the total Contract amount be not thereby decreased or increased in value more than 20 percent. Such variations shall be measured and valued at the rates and prices contained in the Schedule of Quantities and added to, or deducted from the Contract amount. Should there be any dispute as to whether such Order in Writing constitutes a Variation Order in terms of this Contract, the decision of the Engineer shall be final.
(iv) No claim f or any extra or for any addition or for any variation shall be entertained unless such extra, addition or variation was ordered in writing by the Engineer. No objection to the description or terms of an Order in Writing will be entertained unless lodged in writing with the Engineer within 21 days of the date of the
9
Order.
(v) The value of any additional item or items, or of any variation
for which there are no rates or prices in the Schedule of Quantities
will be
adjusted by mutual agreement on the basis of the rates or prices for similar
work appearing in the Schedule of Quantities
or, where no similar work appears
in the Schedule of Quantities, on the basis of the average ruling rates or
prices as determined
by the Engineer for similar work in the Building Industry
in the area in which the Works are situated. The method by which the latter
average ruling rates or prices are determined shall be in the sole discretion of
the Engineer. In the event of a price for any additional
item or items or any
variation being inserted in the order in writing to the Contractor, it will be
understood that he accepts same
unless he lodges a written objection to such
price within 21 days of the date of the order.
(vi) Unless by special agreement entered into between the Engineer and the Contractor, and subject to the production of satisfactory evidence regarding any damages sustained by the Contractor, an amount nót exceeding five per cent of the schedule prices shall be paid on the nett value of the work omitted beyond 20 per cent of the contract amount, caused either by reductions or by variations, or by cancellation of the Contract before or after any work in pursuance of it has been done.
(vii) Should the Contractor be reguested by the Engineer in any Order in Writing to
10
execute any work or to supply any labour or materials which, according to his
interpretation of the Contract, are not provided for
therein, he shall forthwith
give notice, in writing, to the Engineer, that he shall require to be paid for
the same as extra work.
The Contractor shall, however, proceed to act upon such
Order in Writing (unless or until the same be countermanded), so that neither
the execution of the Works nor the supply of material or labour may be delayed
by any difference or controversy on the interpretation
of the Contract; and it
is expressly aqreed that no claim shall arise under this clause unless such
notice as aforesaid shall have
been given in writing to the Engineer within 21
days of the date of the Order in Writing.
4. Where the Engineer shall so
decide, the Contractor will carry out extras and variations on the basis of
daywork, and payment will
be made on the nett value of all materials used, plus
10 per cent thereon, together with the direct labour costs incurred, which
costs
shall specifically exclude the cost of persons administratively employed in the
Contractor's organisation, and to which labour
costs shall be added 33 ⅓
per cent. The percentages mentioned shall be regarded as covering supervision,
Contractor's profit
and the uae of all plant, tools, machinery and
scaffolding.
In addition, all other direct costs reasonably incurred shall be allowed to the Contractor. In all such cases the Contractor will be required to deliver to the Engineer
11
fortnightly a full detailed account in duplicate of labour and materials. One signed copy will subseguently be returned to the Contractor and he must produce same in the adjustment or settlement of accounts. Shouid the Engineer query any such account the Contractor must be notified thereof within seven days of receipt of the account. In the event of such detailed accounts not being so delivered through neglect or default of the Contractor he will forfeit any right to such payment."
The plaintiff commenced work in September 1975, even before the contract documents were formally signed. Numerous working drawings were in due course issued to it, differing in detail from the sketch plans handed to tenderers. Progress payments were made, calculated on the basis of the quoted rates, for work executed in accordance with the amended drawings.
On 25 October 1976 the defendant, again acting through the department, prepared a document, termed a variation order and referred to throughout these proceedings as "variation order 4'' ("VO4"), which was
12
handed to the plaintiff during May 1977 and which read as
follows:
SEE ORIGINAL JUDGEMENT PAGE
13
What was supposedly deleted, under the heading "omit", was the totality of
the work save for preliminary and general items for which
rates were not
quoted.
It was - and still is - the plainkiff's contention that V04 altered
the basis of remuneration for bhe work done, from rates specified
in the
schedule of guantities to remuneration which was to be "fair and reasonable".
The plaintiff accordingly claimed to be entitled
to a further R2 500 093,00, in
addition to the sum of R35 508 861,60, which (but for an amount of R285 748,48,
settled after summons)
had already been paid to it. The defendant resisted the
claim, maintaining that the priced rates, notwithstanding V04, remained firm
throughout. On that issue the matter proceeded to trial.
During the course of inspection of discovered documents the plaintiff's representatives chanced upon certain information which caused the plaintiff to recast its entire claim. A new claim for damages was introduced
14
based on alleged pre-contractual misrepresentations. This became the
plaintiff's main claim; the original claim based on VO4 became
a mere
álternative. In regard to the latter claim the court agreed to test only
the principle, and to leave over its possible
quantification for later
consideration.
The trial commenced in the Transvaal Provincial Division
before Olivier J. It was a protracted one. The record runs into 41 volumes.
Eventually the main and the alternative claims were both dismissed. Leave was
granted by the court a quo to the plaintiff to appeal
to this Court on all the
main issues. In their heads of arguments the plaintiff's counsel abandoned the
appeal against the dismissal
of the main claim based on misrepresentation, so
that this Court, in the result, is only concerned with the claim founded on
V04.
This is how the claim was formulated in the particulars of claim:
15
"6. On or about 25 October 1976 the defendant,
acting through its duly authorised representative, issued a variation order numbered 4 which provided for the remeasurement of all work executed and to be executed by the plaintiff, for the omission of all the work (except preliminary items) described in the said bills of quantities and for the addition of the cost of work as executed in accordance with working drawings issued to the plaintiff. A copy of variation order number 4 is annexed hereto marked 'B'.
7. The plaintiff accepted the instructions contained in Annexure 'B' during or about May 1977.
8. Upon the plaintiff's acceptance of the said instructions the contract sum was impliedly or tacitly varied so as to become a fair and reasonable remuneration for the work executed by the plaintiff."
In response to the defendant's request for
particulars it was stated:
"The terms of the variation are set out in the particulars of plaintiff's claim. It is not alleged that a contract came into existence."
and
"It was implied that if the amount of a fair and reasonable remuneration could not be agreed, such amount would be determined by a
16
court of law.
The plaintiff was also asked:
"Is it Plaintiff' s case that the amount R21 840 000,00 as appears from paragraph 2 of the contract was tacitly varied and that 'a fair and reasonable remuneration' was substituted for the said amount?"
to which the plaintiff replied in the affirmative.
What emerges from this somewhat confusing
exchange is that the plaintiff appears to allege:
(a) a "tacit" variation of the "contract sum" which,
although a variation,
is not a contract;
(b) an implied substitution, for the contract sum, of a
new basis of
remuneration viz. one which was fair and
reasonable but the amount of which
was yet to be fixed
or, failing agreement between the parties, was to
be
determined by a court of law.
(The "contract sum" of R21 840 000,00 was not of course a static figure as would have been the case with a "lump sum contract". The ultimate figure would
17
depend on the final admeasurement of work actually
executed. Such a change
in the amount would not be a
true variation of the contract since it would
occur
naturally in accordance with its terms. (Cf
GRINAKER
CONSTRUCTION (TVL) (PTY) LTD v TRANSVAAL
PROVINCIAL
ADMINISTRATION 1982 (1) SA 78 (A).) What is
presumably
meant by the expression "the contract sum was impliedly
or
tacitly varied" in paragraph 8 of the particulars of
claim is a variation of the contractual provisions
governing the
determination of the final sum to be paid
to the contractor. That provision is clause 3 (iii).
And if clause 3 (iii) is to fall away the quoted rates
would likewise fall away.)
The def endant in its plea admitted that the
plaintiff "accepted the instructions" contained in VO4.
In paragraph 8.2 of the plea it is stated:
"The effect of the variation order (i.e. VO4)
was to confirm that -
8.2.1 the work was to be executed in terms of
18
the working drawing and not provisionally described in the provisional bills of quantities; 8.2.2 the work as executed (according to the
working drawings) was to be measured. 8.3 Every allegation in this paragraph not admitted expressly is denied as if specifically traversed."
Paragraph 10 of the plea specifically
denies paragraph 8
of the plaintiff's particulars of claim.
The plea,
therefore, puts in issue the plaintiff's construction of the meaning of VO4 -
and in particular that the "contract sum"
was "varied" in the manner suggested
by the plaintiff.
Counsel for the plaintiff, in argument, expressly disavowed any reliance on a tacit agreement of variation. (Cf ALFRED McALPINE & SON (PTY) LTD v TRANSVAAL PROVINCIAL ADMINISTRATION 1974 (3) SA 506 (A) at 515 H-516D; 517A-D.) His interpretation of the plaintiff's cause of action - I trust that in paraphrasing it I am not doing his argument an injustice
19
departed somewhat from its presentation in the pleadings: V04 expressly and drastically amended ("scrapped" was the word he used) the quantities in the provisional bills of quantities; since the calculation of the rates by a tenderer (and the plaintiff in particular) was inextricably linked to such quantities, the effective deletion of all the quantities against which rates were inserted, of necessity also erased the rates; what was substituted was the "cost of work"; as a matter of interpretation that meant "cost to the employer" which, bearing in mind the close relationship between the rates and the excised quantities, could not mean the quoted rates and so must mean a fair and reasonable remuneration. Mr Van Streepen, the plaintiff's managing director, (the argument went) understood V04 in that light and since he was agreeable to complete the work on that basis, the plaintiff did not object to V04; and so, when the plaintiff accepted VO4
20
(which was common cause on the pleadings), the contract between the parties was varied by the introduction of a new basis of remuneration. V04, according to counsel's analysis, was an express offer by the defendant to the plaintiff to alter the description of the work and hence the quantities, an offer which the plaintiff duly accepted, so that an agreement partially varying the building contract ensued which, on a proper interpretation thereof, bore the meaning contended for by counsel.
What this approach at least has in common with the pleadings is that it alleges a new agreement between the parties, founded on V04, in terms of which a reasonable remuneration was to be substituted for the agreed rates.
The onus rested on the plaintiff to prove its case that V04, duly accepted, constituted a variation of the contractual provisions relating to payment in respect
21
of the items of work referred to in V04.
The first element of that case is
that VO4 was, or could fairly be construed as, the manifestation of an intention
on the part of
the defendant - whether called an offer or not - to amend the
provisions of the contract by substituting reasonable remuneration
for
rates.
This was the first of the two issues which the court a quo formulated
when discussing this aspect of the matter. According to the
court a quo the
broad issue (whether the parties agreed to modify the contract in the respects
claimed by the plaintiff) contains
two subsidiary ones: (a) whether the parties
had the animus contrahendi to "novate or modify" the existing contract and (b)
whether
the parties had reached consensus on how this was to be done.
The court a quo found in favour of the defendant on both issues.
Counsel for the plaintiff attacked not only the
22
conclusion but also the approach adopted by the court a quo, mainly on two
grounds.
It was said, firstly, that absence of animus contrahendi is a
defence which, as such, should have been, but was not, specially pleaded.
According to counsel the defendant, in its plea, only placed the interpretation
of V04 in issue and not the absence of animus contrahendi.
I disagree. The defendant, in its plea, placed in issue every aspect of the entire edifice which the plaintiff sought to construct on the foundation of the words "cost of work" in V04. In particular, the defendant denied that the parties entered into an agreement to vary the contract. One of the elements of such an agreement is the animus contrahendi. The denial therefore covers that element as well.
Both parties relied on the judgment in BEATON v BALDACHIN BROS. 1920 AD 312 - the plaintiff to show that
23
absence of animus contrahendi should be specially pleaded, the defendant to
confirm that evidence may be led to demonstrate that a
particular document was
never intended to function as a contract but was furnished for an entirely
different purpose.
What was said in that case does not, in my view, support
the plaintiff. There the document, on the face of it, purported to be a
contract.
The party seeking to evade it sought to show, appearances
not-withstanding, that the document had no contractual significance. That
he had
to prove. Here the document, on the face of it, does not purport to be or to
initiate a new contract at all: it appears to
be no more than a variation order
issued pursuant to clause 3 - to which, incidentally, express reference is made
in the document
itself. VO4 purports to be a variation not of, but in terms of,
the contract. It is the plaintiff which seeks to convert it into
something it
does not profess to be,
24
namely, an offer to vary the terms of the contract. That the plaintiff should
plead and prove - not the other way around.
The defendant, by its general
denial of the plaintiff's specific allegations, is not in my opinion precluded
from maintaining that
VO4 was never issued animo contrahendi. I do not,
therefore, agree with the submission of counsel for the plaintiff that the only
relevant issue on the pleadings is the interpretation of VO4.
According to counsel - and this is the second point of criticism levelled against the approach of the court a quo - lack of animus contrahendi arises in one of two ways: where an offer is not intended to be taken seriously (e.g. where an offer is made in jest) or where it is understood between parties that their agreement was to have no legal status (as in the case of a so called "gentlemen's agreement"). In my view these are instances
25
but not a closed list of cases illustrating the proposition that the serious and deliberate intention to establish a contractual relationship is one of the prereguisites to the formation of a valid contract (cf FROMAN v ROBERTSON 1971 (1) SA 115 (A) at 121D). Properly pleaded, it always remains open to one party to show that a document cn which the other reiies in substantiation of an agreement between them, was never intended (by either or both of them) to function as such. The real question in this appeal is whether this is such a case because VO4 is such a document.
VO4 on the face of it appears to be a written variation order issued by the engineer (as defined). As such it was a peremptory order which did not require acceptance by the contractor - indeed, the contractor, being obliged to comply, had no right to object to such an instruction being issued. (Cf GRINAKER CONSTRUCTION (TVL) (PTY) LTD v TRANSVAAL PROVINCIAL ADMINISTRATION,
26
supra, at 93A.) The contractor's right to resist the order, as the plaintiff was reminded in VO4 itself, was contained in clause 3 of the conditions of contract. The objection could be that the order in writing did not constitute a variation order as defined (clause 3 (iii)); or it could be an objection to the "description or the terms of" the order (clause 3 (iv)). The assertion in the plaintiff's particulars of claim that the defendant "accepted" V04, coupled with the defendant's admission, in its plea, that it did so, theréfore amounts to no more than this: that the plaintiff did not avail itself of its limited right of objection. From the mere admission by the defendant that VO4 was accepted by the plaintiff, it cannot be inferred, as counsel sought to do, that the defendant intended VO4 to be an offer to enter into a new contract varying the old, so that the interpretation of VO4 alone was left for consideration. "Offers" are not the only things capable of acceptance. The acceptance of
27
an order does not imply, by itself, that the order was an offer, capable of
acceptance, to conclude a fresh contract, capable of
interpretation.
According to counsel for the plaintiff VO4 was issued by the
defendant "outside clause 3(iii)". He was compelled to say so since a
variation
in terms of a contract, which is a variation of the terms of a contract, would
be a contradiction in terms. But this submission
(that V04 was dehors the
contract) ignores not only the document itself, but also the manner in which the
plaintiff pleaded its case
- and to the extent that the argument adverted,
albeit obliguely, to the 20% excess in value referred to in clause 3(iii), it
lacked
the reguisite factual foundation: it had not been established how much,
if any, of the eventual increase in value above the initial
contract sum was
attributable to V04 (CF MINISTER OF PUBLIC WORKS v W J M CONSTRUCTION CO
(PTY) LTD, supra, at 66 D-H; VAN STREEPEN & GERMS (PTY)
28
LTD v TRANSVAAL PROVINCIAL ADMINISTRATION 1987 (4) SA 569 (A) at 589G-590D). The document, one in a series of variation orders, all of them signed by the regional representative on the same day, is a standard form used by the department for variation orders, it is headed "Variation order - Wysigingsopdrag", and it expressly refers to clause 3, which is the clause in the conditions of contract governing variation orders generally. In paragraph 6 of its particulars of claim the plaintiff acknowledges that V04 was issued by the "duly authorised representative" of the defendant and in paragraph 7 V04 is described as "an instruction". It is implicit in these averments that there was nothing irregular about V04. In my view there can be no doubt that V04 was issued by the department on behalf of the defendant in terms of clause 3(iii), that it was so understood by the plaintiff in its particulars of claim, and that it derives its force, such as it is, from, and not contrary
29
to, the provisions of the contract.
Even so, V04, although issued in terms
of clause 3 (iii), is not a conventional variation order.
True, it omitted,
and thus varied, certain specified items in the bills of quantities, and to that
extent it resembled a typical variation
order. But it differed from a
conventional variation order in that it purported to be both retrospective and
prospective. It was
headed "remeasurement of work as executed" which suggests
retrospectivity. It omitted certain items in the bills of quantities but
immediately thereafter added the work "as executed" - which again
suggests that it related to work already done. The purpose of omitting all the
items in the bills of guantities for
which rates were guoted (i.e. all the items
except the preliminary and general sections) was plainly not to delete the work
"omitted"
from the contract (since this was immediately restored) or to order
completed work to be demolished.
30
By the time VO4 was handed to the plaintiff, in May 1977, a portion of the work had been executed. Such work was not done in pursuance of variation orders formally issued as such, but in terms of the amended working drawings handed to the plaintiff. V04 encompassed those instructions ex post facto. But it also operated de futuro. The bulk of the work had yet to be completed. V04 constituted an instruction, issued as a formal variation order, that all work described in the relevant sections of the bills of quantities would henceforth have to be executed in accordance with the amended working drawings. In that sense V04 was "confirmatory" of the instructions contained, and to be contained, in the amended working drawings (as the defendant pleaded) even though, strictly speaking, it was unnecessary to produce such a document since the amended working drawings were in themselves "orders in writing" for the purpose of clause 3(iii).
31
V04 was not prompted by the engineer in order
to effect specific changes to the
"... Drawings, Specifications and Bills of Quantities, to increase or decrease the quantities of any item or items or to omit any item or items or to insert any additional item or items" (clause 3(iii)).
What
then was its purpose?
The answer to this question in my opinion appears from
the minutes of two meetings, the first site meeting of 10 September 1975, and
a
subsequent meeting, the one immediately preceeding the drafting of VO4, of 29
September 1976.
During the first site meeting, at which the plaintiff was
represented, the discussions relating to variation orders were minuted as
follows:
"Variation orders
The Chairman said that variation orders should be kept to an absolute minimum and would be issued by the Department in terms of clause 3 of the Conditions of Contract - Form P.W. 54. Each proposed variation order should be accompanied by full motivation and an estimate
32
of cost. The actual cost should be determined in terms of clause 3 of the Conditions of Contract. Sodeteg should indicate whether the prices were based on schedule rates or negotiated rates with the contractor."
(Sodeteg SA (Pty) Ltd was the project manager and as such
responsible for the supervision of the contract and the
co-ordination of
all consultant work.)
The proposed procedure required each variation order to
be accompanied by an estimate of costs. That can only mean "costs to the
defendant",
being the only relevant costs i.e. rates where the variation order
related to items of work for which rates were stipulated. If that
procedure was
adopted when V04 was issued, as was most likely the case, the words "cost of
work as executed" as they appear on VO4
simply meant: the costs already incurred
by the defendant in respect of past work and to be expended by the defendant in
terms of
the contract in respect of future work.
This line of reasoning is conf irmed by the
33
minutes of the other meeting referred to, at which
various representatives
of the department, Sodeteg, the
quantity surveyors and the mechanical and
electrical
consultants were present. The meeting was not attended
by the
plaintiff. Nevertheless there was nothing
confidential about it since the
minutes are expressly
referred to in VO4.
The relevant portion of the minutes reads as
follows:
"1. The meeting was convened to discuss the procedure to be adopted in regard to the issue of variation orders on the above contract.
2. Mr. Kaufmann stressed the importance of maintaining a strict financial control over the service and said that any measures that might assist in this control should be adopted. He suggested that a blanket V.O. be issued omitting the service as measured in the Provisional Bills of Quantities and adding back the cost of the service as executed in accordance with working drawings issued or any amendment to these drawings. 3. Generally, variation orders need only be issued when the cost implications of the contemplated changes are such that it will
34
be necessary for the Department to apply to Treasury for extra funds to carry out the work. Site instructions authorising minor changes to the drawings in respect of work measured provisionally in the Provisional Bills of Quantities need not be supported by variation orders.
4. Variation orders should be issued in the
following instances:-
(a) in respect of any additional accommodation or work not shown on the working drawings, e.g. the increased site office accommodation, the diversion of the 350 mm water main across the site and the piling to certain areas of the Power House. (b) in respect of changes being made to any work already built - in particular, where fruitless expenditure may be involved. (c) any changes made in nominated sub-contractor's work which is covered by lump sum contracts or contracts based on Bills of Quantities. Such changes should only be made after the issue of a V.O. authorising the change has been prepared and issued by P.W.D. H.O.
5. In order to assist with cost control,
the
quantity surveyors will prepare an updated
estimate of the scheme as
detailed on
drawings already issued."
From these minutes one can infer:
(a) that the purpose of the meeting was to discuss
35
procedures to ensure better financial control;
(b) that one such method,
suggested by Mr Kaufmann, at
the time the chief quantity surveyor of the department,
was
"that a blanket V.O. be issued omitting the service as measured in the Provisional Bills of Quantities and adding back the cost of the service as executed in accordance with working drawings issued or any amendment to these drawings".
This suggestion was obviously adopted by
the meeting.
(c) that this "blanket variation order" was contrasted
with
regular variation orders which would only be issued
when, generally speaking,
extra funds would have to be
applied for work not shown on existing drawings.
Routine
changes to the work would be effected by means of working
drawings
issued in terms of site instructions.
VO4, drafted immediately thereafter,
was such a "blanket variation order". Its wording follows, almost precisely, the
wording of paragraph
2 of these minutes;
36
and it refers expressly to these minutes. The probabilities, in my view, that
this is so are so strong as to admit of no real doubt.
And if that is so it
means that VO4 was seen by the department, and hence by the defendant, as a
routine administrative measure which
was designed to regularise the position
where work had not been executed in accordance with the sketch plans initially
issued to
the plaintiff but in accordance with the replacement drawings. By May
1977, when VO4 was handed to the plaintiff, all the working
drawings had already
been issued to it. Such working drawings differed in detail from the description
of the work in the bills of
quantities and the sketch plans. Compared to that
description of the work these working drawings, in effect, constituted informal
variation orders which the contractor was contractually obliged to execute. The
purpose of VO4.was seemingly to normalise the contractual
37
position by issuing a formai comprehensive variation
order so as to bring
the legal position in line with bhe
factual one - for instance, by enabling the contractor,
if so advised, to
object when the 20% limit mentioned in
clause 3 (iii) was reached. Whether it
was strictly
necessary to issue a formal variation order in
these
circumstances is not a matter which needs to be addressed
in these
proceedings, since it was issued in fact. The
document could doubtless have
been phrased less awkwardly
and more symmetrically if the description of what
was
"added" followed the pattern of what was "omitted" and
read, for
instance:
"Add: work as executed in accordance with working drawings issued, to the contractor or amended copies thereof, at cost."
Since the bulk of the work had not yet been done it
follows that it was not possible to put a figure to such
costs.
Counsel for the plaintiff argued that the
38
contents of this minute were inappropriate in
interpreting VO4, since at best it provided evidence of
what occurred
"internally" which could not serve to
contradict "the objective construction"
of VO4. But that
is to misconstrue the significance of the minutes. The
minutes are not
relevant as an aid in the interpretation
of an admitted contract; their
relevance relates to
whether a contract had ever been concluded.
Such
evidence, on the authority of BEATON v BALDACHIN BROS.,
supra,
is directly in point:
"Now the general rule is clear: a party to a written agreement cannot vary its terms by parol evidence. But a party to such a writing, which it is sought to use against him, may lead evidence to show that the document in question is not a contract at all, that it was not intended by the signatories to operate as such, but was given for another purpose." - per INNES CJ at 315.
The true significance of these minutes is that they show,
in my view conclusively, that V04 was never conceived by
the department
(representing the defendant) as an offer;
39
or, to phrase it differently, they demonstrate that the department had no
animus contrahendi when, pursuant to the latter meeting,
V04 was drafted and
subsequently issued. And if V04 was not so intended by the reputed offeror, it
could not, by a purported acceptance
(and in the absence of estoppel) mature
into a contract.
(The latter minute, incidentally, also refutes a theory
which the plaintiff's managing director, Van Streepen, advanced, apparently
in
all seriousness, that V04 was issued by the department, omitting the bills of
quantities almost in their entirety, because the
department was disillusioned
with the poor quality of its own bills of quantities on which tenderers were
invited to tender.)
That V04 was a mere routine procedure, never intended by the defendant as an offer of sorts, let alone one to renegotiate, or litigate about, the rate of remuneration, is in line with the evidence of the
40
wibnesses who testified on behalf of the defendant,
Culligan, du Plessis
and to a lesser extent, Burke.
Their evidence relating to VO4 was never
challenged. So,
for instance, Culligan, a quantity surveyor employed
by
the departmeht, stated:
"Now Mr Culligan it was stated here that variation order no. 4 would have been produced because the department realised that its bill of quantities was an incompetent document. What do you say about that? -- Variation order no. 4 was purely a routine variatión order, just as routine as variation order no. 1 omitting the contingency sum which it is stated in the bill of quantities is to be used at the discretion of the architect and omitted in whole or in part. To then issue a variation order omitting that after having already stated in the bill of quantities seems to me to be unnecessary. But the Department of Public Works has always insisted on any work measured provisionally being omitted by variation order and that referred to variation order no. 4, as well as to variation order no. 1. The bill of quantities quite clearly states that all work will be remeasured as built and priced at rates applicable in the bill of quantities, or words to that effect."
(Variation orders no's 1 and 2, drafted on the same date
41
and by the same official as V04, provide for the omission of, respectively,
the contingency sum of R1 100 000,00 and the provisional
sums of R11 506 265,20
in the final summary of the bills of quantities.) Shanahan, an expert called by
the plaintiff, conceded that
he could not dispute that it was standard practice
for the department to amplify provisional bills of quantities with a document
such as V04.
The idea that VO4 was devised as a proposal for a new formula
for payment is heavily against bhe probablities.
Why, as a start, would the
department spontaneously assume the initiative, against its own interests,to
alter the terms of the contract?
There was no suggestion that either party, at
the the time of V04, was unhappy with the specified rates or that the plaintiff
had
approached the defendant to discuss the matter. Why, indeed, should either
of the parties have
42
been anxious to do so? No reason has been suggested other than Van Streepen's far-fetched one that the department did so because it was embarrassed by its own incompetent schedule of guantities. Is it plausible that thé department would have been prepared to discard such a vital part of its elaborately constructed contract, designed to minimise controversy, for such a loose and uncertain arrangement which, on the plaintiff's approach that it has become entitled to "costs plus a mark-up unless the rates prove to be satisfactory", could only operate to the defendant's detriment and would almost inevitably lead to dispute and most likely to litigation? Why settle on "reasonable remuneration" when clause 4 of the conditions of contract has a ready-made formula for payment where rates are inapplicable? No reason suggests itself why the defendant would have been agreeable to abandon, ex post facto, the fixed rates for work which the plaintiff, without protest and on the basis of such
43
rates, had already executed. Why, if it were indeed its intention to amend the basis of remuneration, would the department do so in such a roundabout fashion, by means of a routine variation order, signed only by a regional representative (who it was not alleged was vested with the authorty to enter into contracts on behalf of bhe defendant), without any reguest from or consultation with the plaintiff, and without the requisite prior approval from the State Tender Board or the Treasury? All of this is in stark contrast to the elaborate negotiations which preceded the building of the nurses' home and the conclusion of the "additional works contract", to which I shall presently refer.
The plaintiff did not, in May 1977, when VO4 was released - or indeed until midway through 1981 express unease or dissatisfaction with the rates even though, according to Van Streepen, it was already apparent to him that the excavation of foundations was
44
grossly understated in the bills of quantities and that adequate provision
had not been made for stormwater drainage.
Payments after VO4 continued to be
made by the defendant to the plaintiff and by the plaintiff to sub-contractors
in accordance with
the specified rates, and the plaintiff's representatives
actively participated in measuring the work and completing the required
documentation in order to ensure payment accordingly. Nowhere is it recorded
that such payments were received by the plaintiff without
prejudice to its
belief that the quoted rates no longer applied. Van Streepen's attempt to
explain this omission on the ground that
these were mere interim payments, to be
adjusted in the final account, and which might yet prove to be reasonable, was
disingenuous.
In the event no such adjustments were suggested and the final
account was compiled solely on the basis of the agreed rates. The plaintiff,
as
it
45
happens, incurred a not insubstantial expense in participating in its
preparation. What the plaintiff, surprisingly enough, did not
do, which on its
approach to VO4 one would have expected it to have done, was to submit regular
accounts of its own costs in labour
and material to the department to enable the
latter to verify or appraise those expenses with a view to the preparation of a
final
account on that basis.
The plaintiff, far from being discontented with
the rates, re-affirmed its willingness to execute work on that very basis. In
March
1977, two months before VO4 was delivered to it, the plaintiff wrote a
letter offering to build the nurses' home (which fell outside
the scope of the
work defined in the schedule of quantities) as a variation to the main contract,
and on the same rates as those
quoted in the schedule of guantities for the
hospital building. The defendant accepted this offer and VO 12 was thereupon
issued
adding
46
a new nurses' home and doctors' and matron's quarters
"... at scheduled rates as negotiated with the Secretary for Public Works and your offer set out in your letters dated 15 and 21 March 1977 respectively and in accordance with site instruction no 66551 dated 9 June 1977 and all specifications, Bills of Quantities and Drawings as per attached list as amended, applicable to this service".
This work was completed and the plaintiff was
was R836 889,00.
By July 1981 the work in terms of the main contract had
reached an advanced stage but certain problems had occurred and the plaintiff
threatened to discontinue the work. The parties were eventually able to bridge
their problems and, after due negotiations, a further
contract was entered into,
known as "the additional works contract". The work referred to in this contract
consisted of the completion
of the work due to - have been done in terms of the
main contract. A new
47
basis for payment (whlch was neither fixed rates nor cost plus a mark-up) was
negotiated. On the plaintiff's approach to VO4 this
should not of course have
been necessary at all since a firm basis for payment had already been agreed to
when VO4 was "accepted".
Yet, contrary to what one would have expected if this
had been the common understanding between the parties, not a single word of
this
was mentioned in the documentation or in testimony of the witnesses.
Indeed,
it is a matter for comment generally that, notwithstanding the startling new
contractual course which VO4 supposedly set,
the subsequent documentation is
entirely silent about it. Not once was it raised, either at a site meeting or in
correspondence.
Such silence is not without significance. It tends to
discredit Van Streepen's evidence that the plaintiff regarded VO4 as an
intimation
by the department that the agreed rates should henceforth be
discarded.
48
Yet the plaintiff neither raised it, nor remonstrated with the department. To
explain, as Van Streepen did, that the plaintiff did
not do so because it was
satisfied that "cost of work" would of necessity enure to its benefit, verges on
the artless. One would
have expected the plaintiff to have strenously objected
when the defendant, under the pretext of a variation order, sought to subvert
the rates which the plaintiff calculated so meticulously and which, for it, were
the lifeblood of its contract. That it did not do
so is a strong indication, in
my view, that it never regarded V04 in that light and that the entire claim,
based on the averment
that the rates were superseded by V04, is something of an
afterthought.
(Of course, if the plaintiff had raised it before November 1982
(when, in anticipation of the final account, Exhibit K was written
by the
plaintiff to the department), either as a formal objection or simply to
49
record its contention that the contract was transformed when the plaintiff
acceded to VO4, this litigation might well have taken a
different course. The
plaintiff's attitude might well have provoked a dispute which the engineer would
then have had to determine,
one way or the other, in terms of clause 3(iii).
What effect that would have had, or what the issues would have been if the
defendant,
in its present plea, had declared a dispute along those lines, are
not matters of concern in this case because that did not happen.)
These
considerations, in their cumulative effect, render it unlikely that Van Streepen
could ever have believed, as he asserted he
did, that the department issued VO4
because it was disenchanted with its own bills of quantities and that, by doing
so, it intended
to discard the bulk of it; or that the plaintiff was agreeable
to complete the project on an unspoken new basis of remuneration which
it was
confident would
50
outstrip the rates calculated by it on quantities which it knew to be
inaccurate.
The plaintiff in my opinion failed to establish on a
preponderance of probabilities that VO4 was ever intended by the defendant to
function as an offer to the plaintiff to vary the terms of the contract relating
to payment, which culminated in an agreement of
variation when the plaintiff, by
not rejecting VO4, supposedly accepted it. Animus contrahendi, in short, has not
been proved.
Moreover, there was no evidence whatsoever that the defendant
was agreeable to abandon the advantages of prior agreed rates and to
remunerate
the plaintiff on the basis of a fair and reasonable remuneration, whatever that
may mean. Even amongst themselves the
plaintiff's witnesses were not unanimous
about what this entailed. That was an aspect of consensus - and not of
quantification, as
was suggested. Consensus has
51
accordingly also not been proved.
In my view the court a quo was right in
concluding that the plaintiff failed to establish either that the defendant
intended to agree
to alter the terms of contract or, if it did, that the parties
had reached consensus on what was to happen. Since VO4 was neither
the prelude
to nor the basis of an agreement its "acceptance" by the plaintiff likewise had
no contractual significance.
Failing any agreement to vary it, the existing structure of remuneration
remained firmly in place.
It follows that the appeal is dismissed with costs,
including the costs of two counsel.
P M NIENABER AJA CONCUR:
JOUBERT ACJ) NESTADT AJ) P H GROSSKOPF AJ) NICHOLAS AJA)