South Africa: Supreme Court of Appeal

You are here:
SAFLII >>
Databases >>
South Africa: Supreme Court of Appeal >>
1993 >>
[1993] ZASCA 179
| Noteup
| LawCite
Moscak v N Goodwin Design (Pty) Ltd. (329/91) [1993] ZASCA 179 (25 November 1993)
Download original files |
Case Number 329/91
/al
IN THE SUPREME COURT OF SOUTH AFRICA (APPELLATE DIVISION)
In the matter between:
VLADISLAV
MOSCAK Appellant
and
N GOODWIN DESIGN (PTY) LIMITED
Respondent
CORAM : BOTHA, GOLDSTONE JJA et KRIEGLER
AJA
DATE OF HEARING : 12 NOVEMBER 1993
DATE OF JUDGMENT : 25 NOVEMBER 1993
JUDGMENT
KRIEGLER AJA /...
2 KRIEGLER AJA :
This is an
appeal (with the leave of the court a quo) against a judgment in the Cape
Provincial Division. The appellant was ordered to pay the sum of R9 452,80 to
the respondent with
costs. The judgment is reported (at 1992 (1) SA 167 (C)) and
contains a detailed resume of the facts. The briefest of factual summaries will
therefore suffice.
The appellant orally engaged the respondent to
design the interior of premises in a new shopping complex in Cape Town, and to
design,
manufacture and install furniture and fittings for a restaurant the
appellant intended opening there. Subsequently disputes arose
between the
parties regarding the state of completion of the work and defects to be
remedied. During a joint inspection the respondent
made a so-called "snagging
list" and remedial work relating thereto commenced. Shortly
3
thereafter, and while such work was still in progress, the appellant put the
respondent off the job.
In due course the respondent sued for
payment for the work it had done and the materials it had supplied. Several
alternative formulations
of the claim were pleaded. For reasons which will
become clear in a moment only one thereof need be mentioned. That was that the
respondent was entitled to payment of the contract price which, in terms of a
tacit term, was the fair and reasonable value thereof,
less payments on account
and less the cost of completing the remedial work. On that basis the respondent
alleged a contract price
of R82 315,24 and, giving credit for interim payments
and allowing a deduction for the remedial work contained in the "snagging list"
not yet done when the contract was terminated, claimed payment of R45 615,24.
The appellant denied the tacit term
4 contended for, alleging in
turn that a maximum price of R50 000,00 had been agreed upon. He denied the
value put on the work and
materials by the respondent, alleged additional
defects and counter-claimed the amount by which his payments on account plus the
sum he alleged was due to him for remedial work exceeded the sum of R50 000,00.
In the course of the trial the counter-claim was
abandoned.
The
learned judge found that the tacit term alleged by the respondent had been
proved. That finding was not challenged on appeal.
Counsel were also ad
idem in this court that the trial court's method of assessing the
quantum of the remuneration to be awarded to the respondent was correct.
That was to take whatever fair and reasonable value of the work
had been proved
as the starting point and then deducting from that amount the payments on
account plus whatever had been proved had
to be
5 expended for
remedial work. As the payments on account were common cause the debate in this
court was confined to the first and
last components of the assessment, i.e. the
quantum of the contract price and of the remedial work. With regard to
the first the trial judge found that at least the base figure of the
counter-claim, R50 000,00, had been established. With regard to the second, the
"snagging list" was held to be substantially correct
and only the cost of a
minor additional item of remedial work was also deducted. The simple arithmetic
involved in the calculation
is not challenged.
Ultimately, therefore, this appeal turns on two straight-forward factual issues, namely, did the trial judge err (a) in taking R50 000,00 as the starting point of the calculation; or (b) in deducting the "snagging list" plus the one item?
The answers to both questions are equally
6
straight-forward. As regards the first there is much to be said for the
contention that the pleadings are decisive, the very basis
of the counter-claim
having been a starting figure of R50 000,00 for the work done and materials
supplied. Furthermore there is ample
justification on the evidence for a finding
that the value thereof amounted to no less than that figure. An experienced
interior
design consultant who had designed and supervised the fitting out of
eight other shops in the same complex had done the original
conceptual design of
the appellant's restaurant. Prior to the trial he had visited the premises to
gauge the nature, extent and quality
of the work done by the respondent. He
expressed the opinion in evidence that the prices charged (as detailed in a
schedule to the
particulars of claim) were "fair and in some cases ... I'd go so
far as to say cheap and reasonable." The respondent's
7 managing
director, a quondam architect, and his wife, who had been in charge of
the respondent's office administration, book-keeping and pricing for several
years,
both testified in support of the amount pleaded (R82 315,24). Mr Goodwin
also explained and quantified the cost of the remedial work
(R2 424,40). The
trial judge concluded however that their evidence was flawed in certain respects
and made the award on the lines
set out above.
There is no reason to
say more than that such approach and conclusion certainly did no injustice to
the appellant. The evidence of
the Goodwins and the interior design consultant,
imperfect though it may have been, stood uncontroverted and established a
sufficiently
certain basis on a balance of probabilities for the learned judge's
assessment. In any event cross-examination on behalf of the appellant,
at one
stage at least, was clearly
8 premised on an acceptance of R50
000,00 as the base figure and he made a corresponding concession in the
witness-box. Admittedly
he was not qualified to express an expert opinion as to
quantum, but the form of his pleadings, the conduct of cross-examination
on his behalf and his own evidence served to fix R50 000,00 as the
line which he
had drawn qua litigant.
With regard to the second issue even less need be said. The court a
quo, with the benefit not only of seeing and hearing the witnesses but also
of a detailed inspection in loco, made clear and unambiguous factual
findings. Nothing advanced in this court on behalf of the appellant warrants any
interference
with the finding that the joint compilation of the "snagging list"
and the respondent's uncontroverted quantification of the items
it contained,
were a safe basis for assessing the subtrahend for remedial work. To this
the
9 judge added an item contended for by the appellant at the
price he alleged. Some further additions to the "snagging list" were pressed
on
appeal. They are either trivial or do not fall to be deducted as they relate to
items not included in the computation of the overall
contract
price.
This appeal is dismissed with costs, including the costs of
the application for leave to appeal.
J.C. KRIEGLER
ACTING JUDGE OF APPEAL
BOTHA ]
] AGREED
GOLDSTONE ]