South Africa: Supreme Court of Appeal

You are here:
SAFLII >>
Databases >>
South Africa: Supreme Court of Appeal >>
2000 >>
[2000] ZASCA 37
| Noteup
| LawCite
S M Goldstein & Co (Pty) Ltd. v Cathkin Park Hotel (Pty) Ltd and Another (513/98) [2000] ZASCA 37; 2000 (4) SA 1019 (SCA) ; [2000] 4 All SA 407 (A) (8 September 2000)
Download original files |
REPORTABLE
THE SUPREME COURT OF APPEAL
OF SOUTH AFRICA
Case No. 513/98
In the matter
between:
S M GOLDSTEIN & CO (PTY) LIMITED
Appellant
and
CATHKIN PARK
HOTEL (PTY) LTD 1st
Respondent
DRAKENSBERG SUN HOTEL (PTY) LTD 2nd
Respondent
Coram: SMALBERGER, HARMS AND PLEWMAN JJA
Heard: 29 AUGUST
2000
Delivered: 8 SEPTEMBER 2000
Subject: Delictual
liability of building contractor to owner and third parties
JUDGMENT
HARMS JA:
[1] The appellant, a building contractor of note, was
responsible for the building of a hotel known as the Drakensberg Sun. The land
and building owner is the first respondent and the lessee and operator of the
hotel the second respondent. During the winter of
1988 a fire which had its
source in the fireplace in the lobby of the hotel destroyed part of the complex.
The respondents, claiming
in delict and alleging negligence, joined the
architect, the interior decorator, the project manager and the appellant in an
action
for damages. The case against the other defendants has either been
settled or withdrawn and in the court below Malan J held the
appellant liable to
compensate the respondents for any damages suffered as a result of the fire.
Since the question relating to
quantum was separated from the liability issue,
the instant appeal (which is before us with the leave of the Chief Justice) is
against
that finding only.
[2] The Drakensberg tends to be rather cold in
winter and a fireplace in the lobby must have been an important design feature.
One
can assume that between them the architect and the interior decorator
decided that the ambience of the area and the hotel called
for a rustic look.
In the event, the builder was issued with drawings and instructions to build a
fireplace using a Jetmaster firebox
suitable for an open fire. A railway
sleeper, impregnated with bitumen, had to rest on top of the firebox to form a
mantlepiece.
Above that an ornamental structure consisting of a sheet of
chipboard with decorative but real log ends or butts had to be fixed
to the
masonry which formed the chimney.
[3] As designed, the fireplace did not
comply with the installation instructions issued by Jetmaster with every unit
sold. Of importance
in this case is the following instruction:
“IMPORTANT: Combustible materials should not be fitted within . . .
450 mm above the firebox unless adequate provision is made
to insulate such
materials.”
In a number of respects the rest of the design did also not
comply with the National Building Regulations. For instance, although
the roof
had to be built with wooden shingles, the necessary and prescribed fire
prevention measures did not form part of the design.
The appellant, sometimes
using nominated subcontractors, built the hotel in general accordance with the
architect's plans but in
constructing the fireplace failed to adhere to
Jetmaster's quoted instructions or the National Building Regulations.
[4] The
fireplace was in constant use. The railway sleeper rested on the hottest part
of the firebox and in time the heat caused
the sleeper to ignite. From there
the fire spread into the roof void via a false flue that had been created
between the sheet of
chipboard and the masonry. The rest of the causal chain
need not be related, nor the extent of the damage.
[5] The respondents
relied upon and the court below dealt with a large number of grounds of
negligence. In the light of the view
I take of the matter, it is not necessary
to traverse the whole field and I intend to limit the discussion. It is common
cause that
the appellant -
constructed the fireplace in a manner so as to result in the railway sleeper being mounted directly above and on the lip of the Jetmaster unit;
failed to have regard to the installation instructions supplied by Jetmaster;
constructed the fireplace in a manner so as to result in there being no provision for insulation between the firebox and the sleeper and the other combustible material (the decorative feature).
These facts,
without more, establish at least a prima facie case of negligence. In addition,
although initially in dispute, it became
common cause at least between the
witnesses that the design and construction of the fireplace would have been
manifestly unsafe to
a builder. The initial dispute concerned the question
whether the fireplace was with hindsight or with foresight manifestly unsafe.
Apart from the fact that it is difficult to conceptualise how something can be
manifestly unsafe with hindsight, the witness who
had added the caveat conceded
the point during cross-examination. Malan J also made such a finding and not
only has it not been
shown that he was wrong, I am of the view that he was
correct. In the light of the evidence it avails the appellant not that the
architect or others on site had failed to notice the defective and inherently
dangerous design and construction. This simply establishes
that others may also
have been negligent or in dereliction of their duties. That puts an end to the
first leg of the inquiry as
formulated in Kruger v Coetzee 1966 (2) SA
428 (A) 430E-F namely whether a diligens paterfamilias in the position of
the defendant would have foreseen the reasonable possibility of his conduct
injuring another in his person or
property and causing him patrimonial
loss.
[6] The next step in the inquiry is to establish whether the reasonable
builder would have taken reasonable steps to guard against
such occurrence. The
answer seems to me to be clear. Any reasonable builder would refrain from
building something which is manifestly
unsafe. He would follow the
manufacturer's installation instructions, especially insofar as they related to
safety matters. It
would have been fairly simple to have followed the
manufacturer's instructions or to have placed some or other effective insulation
between the combustibles and the firebox. Since the appellant failed to take
any of these steps, it also determines the third leg
of the negligence
inquiry.
[7] Having found negligence, it is convenient to deal with
wrongfulness (the breach of a legal duty) at this juncture. In this regard
it
is as well to remember that conduct which is lawful towards one person may be
unlawful towards another. The test involves a
value judgment by applying in
the light of all the circumstances the general criterion of reasonableness. The
criterion is based
upon considerations of morality and policy and the court's
perception of the legal convictions of the community. That harm is foreseeable
is a relevant consideration. (See Government of the Republic of South Africa
v Basdeo and Another 1996 (1) SA 355 (A) 367-369.) In spite of counsel's
protestations, it has to be accepted that in general a builder does have
a legal duty to both the building owner and to third parties to refrain from
building something which is manifestly
unsafe. Even builders should not play
with fire or fireplaces. The essence of counsel's argument was that the
appellant had a legal
duty in terms of the contract to build in accordance with
the design of the architect and that having so built it could not be held
liable
in delict. I am prepared to accept for purposes of argument that a building
owner cannot hold a builder liable in delict
if the builder were contractually
required to construct an unsafe structure, although it is improbable that any
building contract
would contain a term (tacit or otherwise) requiring of a
builder to build something which is manifestly unsafe or defective.
[8] The
first problem with the submission is that it is no answer to the hotel
operator's claim. The second problem is that it fails
to have regard to the
builder's obligations in terms of the building contract in question. The
contract consists of a set of standard
conditions of contract and a “bill
of quantities” without quantities but containing additional and qualifying
terms.
On the one hand the contract obliges the builder to carry out and
complete the works in accordance with the contract and the directions
of the
architect, and to his reasonable satisfaction. He must also comply with the
architect's instructions. If he wishes to deviate,
he has to give the architect
due notice. On the other hand, the contract requires the standard of
workmanship to be of the best
and records that the objective of the builder's
appointment is his expert knowledge and he is made responsible for all aspects
of
the construction of the hotel. In particular it states that all commodities
are to be fixed with care and in strict accordance with
the manufacturer's
instructions and recommendations. Should these conflict with other specified
requirements the architect must
be notified forthwith and if anything is
unclear, the necessary clarification must be obtained from the architect - in
either instance
a variation order should be sought.
[9] These terms
indicate that the appellant's approach to its legal duty is based upon an
oversimplification. The contract did not
oblige the builder to build
irrespective of safety concerns. Simple mechanisms were in place to deal with a
case where the architect's
instructions conflict with safety matters and
manufacturers' instructions. Realising his difficulty, counsel sought refuge
behind
the fact that the failure to advise the architect was not a ground of
negligence relied upon in the particulars of claim. This reasoning
is flawed.
Although the failure to notify or involve the owner or architect is not a ground
of negligence, the issue really arises
in the context of the existence of a
legal duty. Because of the nature of the risk and the degree of foreseeability
a prima facie
case of the existence of a legal duty was established. The
appellant wishes to extricate itself by relying on the building contract.
To do
so it had to a duty to adduce evidence in order to upset the prima facie case.
Proof of the contract alone did nothing to
assist it. As far as the evidence
went, it established that the appellant did not act in terms of the
contract.
[10] Another factor relied upon by the appellant affecting the
existence and scope of its legal duty was the employment by the building
owner
of an architect, a safety consultant and others to design, advise and supervise
the works, and the use of nominated subcontractors.
These facts do not absolve
the appellant. They merely indicate that more than one party had a legal duty
towards the respondents
in relation to the safety of the fireplace.
[11] In
my judgment the appellant is on this simple basis liable and without necessarily
agreeing with all the other findings and
rulings of law made by the court below,
it is unnecessary to consider them. The appellant, in anticipation of such a
finding, relied
upon the contributory negligence of the first respondent,
alleging its negligence (i) in approving the design and the choice of material
for the fireplace and roof structure and (ii) in failing to assure that they
would not constitute a fire hazard or cause a fire.
There is no merit in the
partial defence. The evidence does not establish that the first respondent
approved the design details.
A number of independent experts were employed to
design, construct and manage the construction of an hotel. It was not incumbent
upon the first respondent in those circumstances to check independently whether
everyone was doing his work properly and it was entitled
to rely on those who it
paid to do the work.
[12] Finally, the appellant also relied as against
the first respondent upon a provision in the General Conditions of Contract
which
provides in part that “. . . the Contractor shall in no case be
liable for any loss or damage to the said Works, material or
goods caused by an
excepted peril”. One of the excepted perils is “the design of the
Works . . . by the . . . Employer's
servants or agents.” Thus, the
question is whether the damage was caused by the design of the architect.
Having found that
the damage was caused, at least in part, by the negligence of
the appellant who in any event did not comply with its contractual
duties, the
clause appears to me to be inapplicable. Its purpose is to protect a builder
who complies fully with his contractual
obligations and to place the design
responsibility where it should be, namely on the shoulders of the architect.
Its object is not
to create an exemption for a builder who, having acted
negligently, can point to the fact that the design was a contributory cause
of
the damage.
[13] Judgments of this Court often conclude with a lament about
the state of the record. If a properly prepared record, trimmed of
all
unnecessary material and duly cross-referenced, crosses one's desk one notices
it immediately. The record in the instant case
is one of the few that justify
a commendation.
[14] The appeal is dismissed with costs, including the costs
of two counsel.
_________________
L T C HARMS
JUDGE OF
APPEAL
AGREE:
SMALBERGER JA
PLEWMAN JA